Worksheet 06 / frame setting-out
How to fit or replace a door frame
Treat the job as a measured setting-out sequence: identify the assembly, record the opening from a finished-floor datum, dry assemble it, bring it square and brace it. Then enter the top setback, bottom setback and maximum spacing stated for the exact wall, frame and fixing system. This planner distributes marks; it does not choose the fixing or judge the opening.
User-defined fixing marker
The Marked Door · Frame fixing record
Frame Fixing Marker
Plot one jamb or rail
Formula v1.0.0Researched 2026-09-04
Worked example — fixed values
Frame fixing record
- Mark 1: 150 mm from top
- Mark 2: 585 mm from top
- Mark 3: 1,020 mm from top
- Mark 4: 1,455 mm from top
- Mark 5: 1,890 mm from top
Five example marks are plotted at 150, 585, 1020, 1455 and 1890 mm from the top. The 435 mm calculated step is no greater than the example’s entered 450 mm maximum.
Assumptions register
Fixed worked example only: frame height 2040 mm; top setback 150 mm; bottom setback 150 mm; selected maximum spacing 450 mm; fixing/substrate note: example manufacturer job record.
The arithmetic treats the entered height as one straight setting-out rail. It does not choose fixings, identify the substrate, inspect packers, assess the opening or transfer the pattern to a second jamb.
The Marked Door / worked example frame fixing record
Job/reference: ____________________ · Printed date: ____________________
Canonical record: https://neoporte.com/replace-a-door-frame/ · Formula 1.0.0 · Researched 2026-09-04 · Source keys: doorsuperstore-fit-door-frame, doorsuperstore-fit-door-lining, doorsuperstore-replace-door-frame, dhf-timber-doorsets
Current-result print is enabled only after every required entry produces a current finite plot. The blank worksheet is independent and never inherits the live result.
Name the assembly first
Frame, lining and casing are not interchangeable job notes.
First compare door frames and linings. A frame generally means the fixed head-and-jamb assembly; an internal lining receives stops and architrave. “Casing” varies between suppliers and trades, sometimes meaning a prepared set and sometimes decorative trim. Preserve the product wording rather than treating those labels as universal.
The distinction changes what you measure. A rebated frame may already contain the stop profile; a lining commonly receives separate stops later. Decorative architrave covers the joint at the wall face but is not the opening datum. The frame sequence record and lining sequence record are kept separate in the source register because their terminology is not treated as one universal rule. The timber doorset record provides component context without turning this worksheet into a product specification.
Opening and floor datum
Measure the opening as a condition, not one width and height.
Record width near the top, middle and bottom; record height at more than one position; and note diagonals where they help describe squareness. Keep the raw opening record separate from the intended outside dimensions of the frame or lining. A narrow reading, a broad reading and a diagonal difference are observations, not permission to cut masonry or alter a lintel.
Establish what “bottom” means. Mark a durable finished-floor datum or record the build-up still to be added. Thresholds, floor coverings, screed and underlay can change the final reference. Measure all vertical offsets from the same declared line. If the finished level is not known, leave that stage unresolved rather than converting a temporary floor into a final datum.
Use the separate recorder to measure the opening at three points before preparing this fixing sheet.
Dry assembly
Square, brace and recheck before marks become holes.
Assemble the head and jambs in the orientation shown by the product information. Stand the assembly dry and position packers as required by the chosen fixing method. Before you hang the door leaf, check level, plumb, diagonals and the intended opening; brace the assembly so those readings do not drift.
Re-read the opening from the declared floor datum after bracing. A frame can be square while sitting in the wrong vertical position, and a correct head level does not prove both jambs follow the intended plane. Preserve the measured values and any packer locations in the job record rather than relying on memory after drilling begins.
The replacement sequence record is cited only for general removal and checking context. Its example positions are not imported into this planner.
Select the system outside the calculator
Wall, frame and fixing data must describe the same job.
Before entering spacing, identify the frame material and section, the substrate actually present, the fixing product, the required embedment and edge conditions, and the manufacturer document that connects them. Record whether a packer, sleeve, bracket or proprietary anchor forms part of that system. The calculator has no masonry mode, drill mode or concealed fixing catalogue.
Enter the top and bottom setbacks from that chosen information, then enter its maximum permitted spacing. The word “maximum” matters: the formula divides the usable rail into enough equal intervals that the calculated step does not exceed the entered number. It does not preserve a preferred rhythm, avoid hinges, find services or decide whether a proposed hole lands in sound material. Those checks remain part of the physical setting-out process.
Formula register / 1.0.0
How the marks are distributed
usable rail = height − top setback − bottom setbackintervals = ceil(usable rail ÷ entered maximum spacing)actual step = usable rail ÷ intervalsmark[n] = top setback + n × actual stepThe calculation methodology includes both ends of the usable rail. Missing values, a non-positive usable rail, non-finite arithmetic or an impractically large allocation produces no current plot and keeps current-result print unavailable. The plot is capped at 26 marks: its 25 baseline gaps are 16.48 SVG units and labels alternate across two columns, leaving 32.96 units in each column for 12 px text. The A4 register holds 13 lines in each of two columns. Larger results require separate rails.
Fixed worked example
2040 mm frame with an entered 450 mm maximum
For height 2040 mm, top setback 150 mm and bottom setback 150 mm, the usable rail is 1740 mm. Dividing 1740 by the entered maximum 450 gives 3.866…, so the interval count rounds upward to 4. The actual step is 1740 ÷ 4 = 435 mm.
Starting at 150 mm produces five marks: 150, 585, 1020, 1455 and 1890 mm from the top. The final mark is also 150 mm above the entered bottom. These are fixed example inputs, not values inserted into the live spacing field.
Stop before altering the opening
Damage, loose masonry and structural movement stay outside this planner.
Pause for an uncertain lintel, cracking, loose masonry, structural movement, unsupported material or a wall condition unmatched by the fixing data. Stop if the existing frame or any retained component is damaged. A plot is not evidence about load paths or movement; record the issue and obtain relevant building or structural input.
Also pause if the frame appears to restrain loose work, services may cross a mark or enlargement is needed. This page neither assesses those conditions nor turns them into a drilling method.
Blank frame fixing worksheet
Carry a clean record to the opening
Job/reference: ____________________ Printed date: ____________________ Rail: hinge jamb / closing jamb / head / other
| Record | Entered value or note | Transferred mark | Physical location check |
|---|---|---|---|
| Opening and floor datum | |||
| Frame height and setbacks | |||
| Fixing/substrate document | |||
| Maximum spacing and marks |